Asbestos surveys, air monitoring and clearance: what each step is for
How an asbestos project usually runs from survey to clearance, who does each job, and how to keep the testing independent of the removal.
An asbestos project has several distinct phases, and different professionals normally handle each. Understanding the sequence helps you buy only the services you need and helps you spot a bid that skips a step. The steps below describe common practice; the exact requirements depend on your state and your building, so check with the state agency that licenses professionals. This guide is general information rather than technical or legal advice.
1. The survey: find out what is there
An asbestos survey or inspection identifies suspect materials, samples them and sends the samples to a laboratory. The EPA notes that you cannot tell whether a material contains asbestos by looking at it, and recommends that a professional take the samples. Inspectors are accredited under the state’s program: in Connecticut, for example, the credentials in the state file include an Asbestos Consultant-Inspector and an Inspector/Management Planner. The result is a written report listing materials, locations, quantities and condition.
For most buildings other than residential buildings of four or fewer units, the survey is not optional. The EPA’s asbestos NESHAP, 40 CFR 61.145, requires the owner or operator to thoroughly inspect the affected part of the building before any demolition or renovation, including nonfriable materials such as floor tile and roofing. Some states also say who may do it: in Florida, only a licensed asbestos consultant may conduct an asbestos survey.
Ask the inspector to survey the whole area you plan to disturb, not just the obvious materials. Hidden layers such as flooring adhesive, pipe insulation above ceilings or wall plaster are common surprises.
2. The scope or project design
For larger projects, a project designer (or the inspector) writes the abatement scope: what to remove, how to contain it, how waste will be handled and what the finished area must look like. Small residential projects may use a simpler written scope. Either way, the scope should be written by someone with no financial stake in the removal, so that contractors can bid on the same specification.
3. Notifications and permits
The EPA says the owner or operator of a building must notify the appropriate state agency before demolition and before renovations involving more than a threshold amount of asbestos material. It applies to most buildings except residential buildings with four or fewer units, and state and local rules may go further. Ask the contractor who will file any notification and get a copy.
4. Abatement: the removal itself
Licensed abatement contractors seal the work area, control air movement, wet or otherwise control the material, remove it, and bag and label the waste. The EPA notes that asbestos operations must not have visible emissions unless air is properly cleaned, and there are requirements for asbestos waste. Supervisors and workers need state credentials, which is why a good contractor will readily provide proof for the crew.
5. Air monitoring during the work
On many projects a separate consultant, sometimes called a project monitor, checks air quality and observes the contractor. In Connecticut’s state file, for example, project monitor and project designer are distinct consultant credentials. Independent monitoring is valuable because the person watching is not the person paid to finish quickly.
How samples are analysed
Bulk samples of building material are normally examined by polarized light microscopy (PLM). Under the federal rules a material is asbestos-containing when it has more than 1 percent asbestos by that method, and for friable material a result below 10 percent should be checked by point counting, a more exact way of reading the slide.
Air samples are collected on filters and read in one of two ways. Phase contrast microscopy (PCM), using NIOSH Method 7400, counts every fibre that meets its size rules; NIOSH notes that it does not tell asbestos apart from other fibres. Transmission electron microscopy (TEM) can identify asbestos structures and is the reference method for school clearances. For schools, the EPA’s AHERA rule requires TEM work from a laboratory accredited by the National Institute of Standards and Technology, or, where PCM is allowed, a laboratory in the American Industrial Hygiene Association’s proficiency testing program. Ask which lab will be used and how it is accredited.
Do not confuse worker limits with clearance. OSHA’s limit of 0.1 fibres per cubic centimetre over an eight-hour shift protects the crew inside containment; it is not a standard for letting occupants back in.
6. Clearance
When removal is finished, the area is visually inspected and, depending on the project and jurisdiction, air is sampled before people return. Clearance should be signed off by a qualified person who does not work for the abatement contractor. Clearance samples are usually taken with aggressive sampling: under the EPA method, surfaces are swept with the exhaust of a leaf blower and fans keep the air moving while the pumps run, so that settled fibres are caught.
The best-known numbers come from the AHERA rule for schools, 40 CFR 763.90. A school project passes when five TEM samples from inside the work area are not significantly higher than five taken outside at the same time, or when the five inside samples average no more than 70 asbestos structures per square millimetre of filter, provided enough air was drawn. Projects up to 160 square feet or 260 linear feet may instead use PCM, with each of five samples at or below 0.01 fibres per cubic centimetre. Connecticut’s regulations (section 19a-332a-12) apply similar criteria to all buildings, allowing PCM for projects up to 1,500 square feet or 500 linear feet.
Ask in advance what standard will be used and what happens if the area fails: usually the contractor cleans again at its own expense, but write that into the contract.
7. Paperwork you should end up with
- The survey report and lab results.
- The scope or design and the signed contract.
- Copies of the contractor’s license and the workers’ credentials.
- Any notification filed with an agency.
- Waste documentation showing where it went.
- Air-monitoring and clearance results.
Keep them with your property records. If you later sell, insure or renovate again, they show what was found and how it was handled.
Who to call
Use our directory to find licensed consultants and abatement contractors in your area, keep the two roles separate, and read our hiring checklist and guide to when to test. If a bid seems to skip the survey, monitoring or clearance, ask why.
General information only, current as of the date above. The information on Asbestos Abatement Index is not a recommendation or a guarantee of anyone's work. A license record shows registration status on the date shown, not workmanship, insurance coverage at the time of your job, or suitability for your project. Confirm license, insurance and permits directly before you hire. Rules and programs change; check the official sources linked in this guide.